1. A qualifying repair is a repair of a house subject to a Scottish Secure Tenancy or a Short Scottish Secure Tenancy which is repair specified in column 1 of the Schedule below and is the responsibility of the landlord.
As we strive to provide an excellent repairs service to our tenants, we would ask that in instances where a tenant is unhappy with their repair they contact us first and allow us the opportunity to put matters right.
2. The scheme relates to repairs as detailed in the Schedule below which cost no more than £350.00.
3. The Right to Repair Regulations specify that in certain circumstances a tenant may have the right to appoint a second contractor to carry out a reported qualifying repair.
Where a blockage or other problem is found (on inspection or repair) to be the fault of the tenant, the costs will be recharged to the tenant.
| (Defect) | (Maximum period in working days from date immediately following the date of notification of qualifying repair or inspection) |
|---|---|
| Blocked flue to open fire or boiler | 1 |
| Blocked or leaking foul drains, soil stacks or toilet pans where there is no other toilet in the house. | 1 |
| Blocked sink, bath or drain | 1 |
| ELECTRIC POWER | |
| Loss of electric power | 1 |
| Partial loss of electric power | 3 |
| Insecure external window, door or lock | 1 |
| Unsafe access path or step | 1 |
| Significant leaks or flooding from water or heating pipes, tanks, cisterns | 1 |
| Loss or partial loss of gas supply | 1 |
| Loss or partial loss of space or water heating where no alternative heating is available | 1 |
| Toilet not flushing where there is no other toilet in the house | 1 |
| Unsafe power or lighting socket, or electrical fitting. | 1 |
| WATER SUPPLY | |
| Loss of water supply | 1 |
| Partial loss of water supply. | 3 |
| Loose or detached banister or hand rail | 3 |
| Unsafe timber flooring or stair treads | 3 |
| Mechanical extractor fan in internal kitchen or bathroom not working. | 7 |
4. Timescales will start at 9am on the next working day following the day the repair is reported and will end at 5pm on the end day.
The timescales and rules are not always the same. The following will have an effect on the operation of the scheme. Tenants will be informed if there are any changes due to the criteria below.
5. Compensation
Where the primary contractor has failed to carry out the qualifying repair by the last day of the maximum period the landlord shall pay to the tenant a sum of compensation calculated in accordance with paragraph (2).
The amount of compensation referred to in paragraph (1) shall be the sum of:
(a) £15.00; and
(b) £3.00 for every working day, if any, in the period:-
subject to a maximum amount of compensation of £100.00.
Compensation due will be paid to a tenant by the Association without the tenant having to claim for it.